150 TPD Quick Lime Plant in Uzbekistan

February 24, 2020

150 TPD Quick Lime Plant in Uzbekistan
Brief Introduction
Location : Uzbekistan , Tashkent
Project: 150tpd lime plant
Time: October, 2013
Equipment: rotary kiln, vertical preheater, bucket elevator.
Raw material: limestone
Capacity: 50,000tpy
Situation: under installation
 
Project introduction
Cutomer has visited us at October, 2013. Then we have got the order of vertical preheater, bucket elevator and refractory. The customer has an old rotary kiln (φ2.5×40m). This is a reconstruction project, now it's under installation.
 